All the main consents are in place | |
Financial Investment decision | Q3/2014 |
Onshore substation site preparation: commencement | Q3/2014 |
Onshore cable construction | 2015 |
Foundations installation | 2016 |
Offshore cables installation | 2016 |
Turbines installed | 2017 |
First electricity to National Grid | Q1/2017 |
Fully commissioned | end 2017 |