| All the main consents are in place | |
| Financial Investment decision | Q3/2014 |
| Onshore substation site preparation: commencement | Q3/2014 |
| Onshore cable construction | 2015 |
| Foundations installation | 2016 |
| Offshore cables installation | 2016 |
| Turbines installed | 2017 |
| First electricity to National Grid | Q1/2017 |
| Fully commissioned | end 2017 |