Sent by: Captain “Mr. W. van der Meulen” on “Oleg Strashnov”
Date: 20th of March 2016 until 30th of August 2016
Wave Buoy Deployment By Seaway Heavy Lifting
SHL has deployed one wave measurement buoy at the location 53° 17.294'N 001° 25.108'E on the 20th March. Geodetic datum used is WGS84.
DUDGEON OFFSHORE WIND FARM CONSTRUCTION WORKS
NOTICE IS HEREBY GIVEN that construction activities are in progress at the Dudgeon Offshore Wind Farm and Export Cable Corridor
Duct preperation for export cable installation into Horizontal Directional Drilling duct
Notice is hereby given that VBMS will carry out the preparation works for the export cable installation as part of the preparations for the installation of the Dudgeon Offshore Wind Farm.
Duct preparation
VBMS will carry out preparation works for the export cable installation as part of the preparations for the installation of the Dudgeon Offshore Wind Farm.
Wave Buoy Deployment
Partrac will deploy one wave measurement buoy at the location below from 4th March, weather permitting.
Duct preparation for export cable installation into Horizontal Directional Drilling
Notice is hereby given that VBMS will carry out the preparation works for the export cable installation as part of the preparations for the installation of the Dudgeon Offshore Wind Farm. Two ±1170m HDD ducts that have already been installed will be prepared for the export cable installation.